PUMP INSTALLATION AND OPERATIONS
Considerable attention must be paid to proper pump installation to
ensure trouble-free operation. The following factors must be taken into
consideration:
INSTALLATION OF PUMP:
- The pumps should be
accessible for inspection and maintenance and should include valves on
both suction and discharge lines. they should be removed from areas
that are subjected to flooding, water leakage, and corrosion; they
should be located as close as possible to the source of supply and
headroom should be provided for lifting the rotor and casing. If
the pumps must be located in areas of high humidity, the motors must
be designed for this purpose.
- The pump is provided with a
steel baseplate to which the pump and motor are attached. This
baseplate must be bolted securely to the foundation. In most cases,
larger bases are grouted into place, but this may not be required on
smaller units if the foundation is rigid and the baseplate can be
bolted down securely.
- The piping should run to a pump
as directly as possible, avoiding sharp bends. Entrance to the pump should
be provided with long-radius ells or bends to reduce inlet friction to a
minimum, and the suction piping should run straight into the pump.
- Piping must be supported to
take the strain from the pump and provide for expansion and contraction to
avoid pump misalignment. Expansion joints or loops should be used when hot
liquids are being handled.
- The suction piping should be
large enough to minimize the friction losses. Short suction lines are
recommended but are not always possible. In order to avoid problems
experienced with long intake pipes and high suction lifts, an individual
suction line should be provided for each pump. If this is impractical, the
suction-header size should be approximately 50 percent larger than the
pump connection and should be reduced at the pump flange. The use of tees
or right-angle fittings should be avoided, and long radius ells or bends
should be used instead.
- The suction header should be
sloped upward from the reservoir to the pump, and high spots in the
header, where air might collect, should be avoided. The suction end should
be flared, and the suction inlet should be well below the low-water level
to eliminate the possibility of air entrainment. The suction should not be
located close to the point of makeup or returning water, since eddy
currents may interfere with pump operation. When supplying two or more
pumps from a long intake header, a tapering header with Y branches to the
pump suction should be used. For pumps operating under high suction lift,
stuffing boxes should be sealed, using water taken from the discharge
header or from a separate source of supply.
- The suction lift should be
limited to 10 to 15 ft, since only clean cold water can be raised this
amount without experiencing operating difficulties. For hot water, it is
necessary to bring the water to the pump under a positive head. The
velocity should be low, and a suction head of 10 to 20 ft is desirable.
When starting up new boiler-feed water or high-temperature-water
circulating pumps, a strainer is frequently installed to prevent foreign
material from getting into the pumps (and lines) or clogging the suction
intake.
- The strainers can be removed
when the system is cleaned. All strainers should be inspected
periodically.
- A pump that has its suction
line below the pump centerline requires priming that is, the air must be
evacuated from the pump suction before water will enter the pump and fill
the piping and casing. Priming may be accomplished by filling the suction
piping with water from some other source. When water is ejected in a
steady stream, it may be assumed that the pump is full of water, and the
pump may be started, after which the discharge valve may be opened slowly.
If a vacuum pump is used, it should preferably be a wet vacuum pump, since
water may damage a dry vacuum pump.
- To ensure successful
operation of a pump, it should be set on a foundation that is substantial
and rigid enough to permit the pump to absorb vibration. Good foundations
are usually made of concrete. Before the concrete is poured, the
foundation bolts are secured.
- To prevent the bed plate
from springing out of line, the pump must be aligned carefully. Pumps that
come already mounted on a bedplate should be leveled before they are
placed in operation. Pumps that are to be set on a rough foundation should
be set approximately in location and leveled with shims before the
bedplate is grouted in position. Commercial grouting is readily available
with recommended curing periods. Next, check suction and discharge
flanges to determine if they are level.
- After suction and discharge
flanges have been bolted up, the alignment should be checked again. If
connecting of piping has caused misalignment, repeat the procedure
followed previously.
- Check pump and motor
rotation and insert bolts in flanges and connect up. A short time after
the pump has been in operation, the alignment should be checked again.
After it is certain that all is satisfactory, the unit can be doweled. The
doweling is done with tapered pins usually provided with the pump. Dowel
pins are located in the feet of the pump and driver, as well as in the
bedplate.
OPERATION OF PUMPS:
- Before operation, after all piping has been connected and after the baseplate has been bolted in place, the pump and motor should be aligned with a dial indicator to ensure that operation is free from vibration. Any misalignment will cause vibration that could lead to bearing and mechanical seal failure.
- When the alignment is being checked, and with the coupling disconnected, the direction of rotation should be checked. This check also can be made with the coupling connected. however, the pump must be filled with liquid to prevent running the packing or seal dry. A mechanical seal can fail in a short period of time if it is run dry.
- Before placing the pump in
operation, make certain that bearings are lubricated. Rotate the motor by
hand to make certain everything is free. Prime the pump and fill the pump
full of liquid, and with suction valve open and discharge valve closed,
start the pump, noting suction and discharge pressures. (All pumps should
be fitted with pressure gauges on both the suction and discharge sides.)
After running the pump this way for a minute or two with the air vent
open, close vent valves and open the discharge valve slowly.
- Observe gauges closely, and
if anything unusual occurs or pressures seem unusual, stop the pump and
check it thoroughly.
- Start and stop the pump
several times and observe performance. If all looks satisfactory, continue
to operate for 1h to 1 hour, meanwhile observing bearing temperatures and
watching gauges, lubrication, and general actions of the pump and motor
for overheating. Then shut the pump down, recheck alignment, tighten all
bolts, and give the entire installation a careful check. Place the pump
again in operation.
- observe the packing gland,
gland seals, lubrication, and overheating. Never run a pump for an
extended period of time with the discharge valve closed unless the vents
are open or the pump is equipped with a bypass to permit some water to
circulate through the pump at all times.
0 Comments